500 t/d Cement Plant

ApplicationCement Plant, Thermal Power Plant
Annual Output150,000 tons
Process TypeNew Dry Process
Blaine 3300-3800 cm²/g

Overview

500 TPD cement plant include the steps of crushing, cement raw Material preparation and homogenization, pre-heating and decomposition, clinker calcination, cement grinding and cement packing. The design of 500 tpd new dry process cement production line contracted to build by Xinxiang Great Wall Machinery Co., Ltd adopts the dry process, which helps to reduce power consumption by 20% to 30% thus creating more profits for the user company.

 Features

Most advanced production technology 

The design of 500t/d new dry process cement production line contracted to build by Xinxiang Great Wall Machinery Co.,Ltd adopts the most advanced five-stage suspension preheater, RSP/F calciner and NSP rotary kiln. The large kiln hood increases the temperature of tertiary air effectively and makes the layout of tertiary air duct simple.

Turnkey Solution

Great Wall Machinery has an industry-leading technology team and  in  close collaboration with chief experts of vertical roller mill. Therefore, we can provide EP project according to the actual situation of the customer.

Timely Delivery 

We have large-scale steel casting workshop and machining workshop, which ensures the equipment used in cement plant with high quality, and reduces project time. 

 Configuration

No.EquipmentModelQuantity(set)Amount
1Limestone Crusher (Jaw Crusher) 1 
2Hammer Crusher 1 
3Raw Material Vertical Roller MillGRMR22.311 
4Coal Vertical Roller MillGRMC12.211 
5High Temperature Fan at Kiln Inlet 1 
6Electrostatic Precipitator at Kiln Inlet 1 
7Preheating and Precalcining System at Kiln Inlet 1 
8Rotary Kilnφ3.0x45m1 
9Horizontal Pushing Grate Cooler 1 
10Cement Ball Millφ2.4x13m1 
11Packing Machine 4BBX(SG) Four Nozzles Fixed 1